Using Graphic Indicators in Primavera Software

Using Graphic Indicators in Primavera Software

We want to display activities that are 100% completed with a green symbol and activities that are in progress and not started in blue. For this, you need to create a custom indicator column. From the Enterprise menu, enter the user defined field window, click the add option and create a custom field called progress status. The type of this field is Indicator.

شرکت همیار پروژه صنعت و ساختمان اذربایجان

Insert the newly created column into the project.

شرکت همیار پروژه صنعت و ساختمان اذربایجان

Select Global Change from the Tools menu

From the New window, select a new title for writing the formula and click the Modify option

After confirming the formulation, a preview will be displayed as below. If you approve it, you can press the Commit Changes option and apply the changes in the software